Giant army packages face a coordination drawback when taking up broad and interdependent program aims. Whereas small packages with decoupled groups can usually depend on a extra ad-hoc strategy to planning and roadmaps, massive packages with complicated dependencies usually should develop grasp schedules that may embody as many as 50,000 parts. In such an surroundings, groups want to have the ability to coordinate efforts and meet cross-cutting aims. Within the absence of higher instruments, when tasked with a serious program goal, groups flip to PowerPoint to stipulate quarterly actions. Whereas such an strategy affords some visibility into program actions, the top result’s a slide deck that will solely be present for 4 days per 12 months, since there is no such thing as a direct mechanism for updating the doc between quarterly updates. Along with creating overload, this strategy is insufficient to reply three crucial questions:
- Is there something you deliberate to finish final quarter however didn’t? In that case, what’s the affect?
- How assured are you about finishing commitments this quarter?
- Is there anybody you might be depending on, and are they conscious?
In aviation, waypoints information pilots by way of complicated flight plans, offering construction whereas sustaining flexibility. Impressed by this aviation precept, I labored with Lieutenant Colonel Adam Satterfield of america Air Power to create a light-weight digital framework that may assist main packages plan, observe, and execute main aims. This put up explains how the Waypoints Framework can present program managers with a light-weight digital strategy to visualizing main actions, synchronizing dependencies throughout groups, and managing dangers.
The Origin of Waypoints
As a Program Administration Officer in america Air Power, Lieutenant Colonel Satterfield oversees main protection packages. Lt. Col. Satterfield, a co-creator of Waypoints, had a sheet of paper hanging up in his cubicle that outlines the concepts that grew to become the origin of Waypoints. Lt. Col. Satterfield had beforehand met with the Colonel in command of his main program, who listed three necessities for Waypoints:
- It must be easy.
- It must be led by the workforce leaders.
- It wants to visualise the work.
To attain these necessities, Lt. Col. Satterfield understood {that a} minimal viable framework was wanted to bridge the hole between casual planning and complete undertaking administration. The framework wanted to have the ability to deal with coordination wants with out overwhelming the group.
Lt. Col. Satterfield started collaborating with us, and our preliminary step was to consolidate our planning efforts in Excel. Whereas this shift improved dependency visibility and created a single supply of knowledge, quarterly accuracy issues endured.
The breakthrough got here after we migrated to Jira and Confluence. Jira allowed us to trace particular person waypoints as points, whereas Confluence supplied data administration and dynamic dashboards. It allowed groups to filter waypoints into quarterly buckets, type by due date, and hint paths towards objectives, lowering cognitive overload whereas enabling steady updates.
Extra importantly, this digital strategy essentially modified the group’s planning mindset. As an alternative of ready for quarterly critiques to find {that a} milestone had been missed, program managers now had perception into points and progress in close to actual time. Groups might modify course instantly as soon as a difficulty arose relatively than discovering issues months after they emerged.
Far too usually, program managers mistakenly ask, Are we the place we need to be? As an alternative, they need to be asking, Are we on the correct trajectory?
The mindset related to the primary query concerned lacking a mark earlier than correcting course. The latter permits for corrections en route, much like a pilot adjusting the heading of an airplane between waypoints relatively than discovering that they missed their vacation spot as a result of the winds pushed them astray.
Constructing the Waypoints Framework
The Waypoints Framework makes use of a light-weight digital strategy to visualise main actions, synchronize dependencies, and handle dangers. Jira and Confluence are the 2 main digital instruments that allow the framework. The Waypoints journey usually begins with a objective {that a} program needs to attain in two or three years that’s usually made public due to its significance to your entire group, comparable to the primary flight of the B-21 stealth bomber in November 2023. Reaching that main objective requires the hassle of a number of groups.
Every workforce in this system enterprise establishes its personal waypoints main towards this main programmatic objective, which creates a visual path that everybody in a company can comply with. Every waypoint represents a promise, a deliberate exercise that unlocks one other programmatic exercise towards a objective.
The Waypoints Framework rests on three ideas:
- Proper-sizing: To assist distill complexity to a understandable stage, the group’s workforce leaders will establish two-to-eight actions per quarter per workforce with these groups sustaining detailed planning utilizing no matter instruments work finest. When too many actions are deliberate, the hassle to take care of correct plans will increase. Retaining the quarterly deliberate accomplishments to single digits helped make sure the plan’s accuracy. For every exercise, every workforce will establish their definition of completed and description main contributions in the direction of the most important programmatic objective set forth. This step alone can usually be an early indicator of mismatches and incorrect handoffs.

Determine 1: The primary precept, right-sizing, limits the variety of actions per quarter to enhance plan accuracy.
- Time-phasing: The Waypoints Framework requires high-fidelity planning for the present quarter plus the subsequent two, medium-fidelity for the next two six-month intervals, and lower-fidelity for subsequent twelve-month intervals. This retains near-term work sharp with out losing effort on distant aims the place uncertainties might stay.

Determine 2: The second precept, time-phasing, places the best constancy within the near-term phases of the plan.
Uncover issues early: Mapping dependencies between every workforce’s waypoints [HAB1] [KD2] identifies coordination gaps and bottlenecks earlier than they turn into crises. Moreover, “orphan” waypoints are actually simply noticed. Whereas the exercise should be vital to the group, if it’s not crucial to attain the most important programmatic objective, it must be thought-about for removing from the sight image, as a way to preserve a easy view of crucial actions to achieve the objective. Whereas the exercise should be vital to the group, if it’s not crucial to attain the most important programmatic objective, it must be thought-about for removing from the sight image. This helps preserve a streamlined view of crucial actions essential to achieve the objective.

Determine 3: The third precept, uncover issues early, maps dependencies between waypoints to establish gaps and bottlenecks.
We realized that for organizations to efficiently undertake Waypoints, they would want three crucial management and workforce commitments:
- management endorsement with out mandate (creating “pull” relatively than “push”),
- a lean motivated launch workforce, and
- a assure {that a} workforce’s updates to their waypoints will take not more than 5 minutes.
With these commitments in place, as proven under with our early-adopter groups, Waypoints replaces the dreaded quarterly PowerPoint replace.
Piloting Waypoints and the 5-Minute Assure
To pilot the Waypoints Framework, we recognized three early-adopter groups that have been fluent in digital instruments like Jira and Confluence. After sitting down with these three groups and figuring out their waypoints in addition to upstream and downstream dependencies, inside 1 / 4, we have been in a position to efficiently launch their packages into this framework and show the good thing about visualizing their actions in light-weight digital instruments.
The workforce leaders who piloted Waypoints shortly realized that it allowed them to be prepared for any programmatic assessment inside 5 minutes, a big worth proposition as they beforehand had spent one-to-two days getting ready PowerPoint slides every quarter.
Waypoints additionally considerably improved workforce communication. We introduced Waypoints as a collaboration device—not a piece tracker—an important distinction that decreased adoption resistance. Leaders within the early adopter organizations inspired however didn’t mandate adoption, and groups proved receptive to new approaches.
Waypoints identification workshops helped groups visualize plans and perceive scope. We carried out dependency mapping workshops that uncovered incomplete handoffs early, enabling plan corrections earlier than issues materialized.
The groups that piloted Waypoints additionally grew to become disciplined about scoping, capturing solely the work important to programmatic objectives.
Scaling Challenges and Options
Adoption inside the group was so profitable that the Launch Workforce grew to become a constraint in serving to groups construct their waypoints and dependencies between groups that should be visualized and managed to make sure handoffs are profitable. In piloting our framework, we realized that we wanted to establish at the least one change agent on every workforce and empower them to be taught the digital tooling to assist scale the hassle. As an alternative of groups ready on the Launch Workforce’s calendar availability, we might have unfold the hassle extra evenly throughout the group.
We additionally got here to grasp that we wanted to have a plan to transition to execution of the work. A transparent level of contact inside the group should be recognized because the individual accountable and empowered for orchestrating all groups’ actions as a way to attain the most important programmatic objective.
Even in a company that has a excessive belief tradition, we discovered that configuration management of the Jira knowledge grew to become essential. Our enterprise intelligence depends on the accuracy of the info, so we discovered that assigning an information steward (i.e., a person who actually understands the community of waypoints that may result in profitable completion of the objective) to be essential.
Future implementations of the Waypoints Framework will incorporate the designation of workforce members to every of those key roles, constructing upon the always-evolving, always-improving blueprints we be taught when packages embark on the Waypoints Framework journey.
Inquisitive about Adopting Waypoints?
Working in acquisition requires a endless cycle of reporting that leaves little time to give attention to fixing issues or attaining objectives. The Waypoints Framework is designed to streamline that course of and permit program managers to give attention to their mission objectives, usually with their current program administration instruments.
Efficient program administration mustn’t require large paperwork. Impressed by a routine navigational idea from aviation, we now have created a framework that enables protection packages to attain formidable aims by way of incremental coordinated packages. In piloting the Waypoints Framework, we realized that each organizational setting is a novel journey that may require changes. One good thing about working on the SEI is that by way of our work with main protection packages, we now have encountered and gained an appreciation for diverse buyer environments and understanding the distinctive tailoring that can be required for every state of affairs.